Assosa Town Internal Asphalt Maintenance and Design Build Road Project

Project Name: Assosa Town Internal Asphalt Maintenance and Design Build Road Project
Signing/Commen cement Date: 09 Nov 2021
Completion Date: 9-Nov-2023
Contract Duration: 24 Months
Todate Progess in Amount: 105,260,518.79
Contract Amount: 1,158,786,508.29
Todate Progess (%): 9.00%
Remaining Amount: 1,053,525,989.51
Status: Under Progress

Weybo Lot II Irrigation & Drainage System Construction Work

Project Name: Weybo Lot II Irrigation & Drainage System Construction Work
Signing/Commen cement Date: May-21
Completion Date: May-23
Contract Duration: 24 Months
Todate Progess in Amount: 53,532,279.38
Contract Amount: 1,031,374,587.03
Todate Progess (%): 4.52 %
Remaining Amount: 977,842,307.65
Status: Under Progress

Addele Sekina Rural Road Project: Contract 2- km 21+000~36+132 .

Project Name: Addele Sekina Rural Road Project: Contract 2-km 21+000~36+132
Signing/Commen cement Date: Feb-21
Completion Date: Aug 26,2023
Contract Duration: 30 Months
Todate Progess in Amount: 395,256,811.78
Contract Amount: 504,257,437.39
Todate Progess (%): 92.6 %
Remaining Amount: 109,000,625.61
Status: Under Progress

Humbo Tebela - Abaya Design and Build Road Project

Project Name: Humbo Tebela - Abaya Design and Build Road Project
Signing/Commen cement Date: May-20
Completion Date: 16-Apr-2023
Contract Duration: 36 Months
Todate Progess in Amount: 310,618,927.22
Contract Amount: 699,000,000.00
Todate Progess (%): 44.4%
Remaining Amount: 388,381,072.78
Status: Under Progress

Yabelo~Metagefersa~Shakiso ,Contract 2:Oblo~Dermi Road Project

Project NameYabelo~Metagefersa~Shakiso ,Contract 2:Oblo~Dermi Road Project
Signing/Commen cement Date: Jul-18
Completion Date: Oct-21
Contract Duration: 1095 Cal. Days
Todate Progess in Amount:630,033,906.21
Contract Amount: 893,493,928.98
Todate Progess (%): 100%
Remaining Amount:
Status: Completed

Dambi-Doolo Town Internal 12km Asphalt Concrete Road Project

Project NameDambi-Doolo Town Internal 12km Asphalt Concrete Road Project
Signing/Commen cement Date: Feb-14
Completion Date: APr-20
Contract Duration: 2,267 Cal.Days
Todate Progess in Amount: 235,150,126.27
Contract Amount: 257,191,301.14
Todate Progess (%): 100%
Remaining Amount:
Status: Completed